Changing the face of Charleston : The unbuilding of the Grace and Pearman Bridges
Frank's Internet Home Page
Blog: 2005
Archives of unbuilding sections
Blog: 2006
The story of building the Ravenel Bridge
Visit our
Adventures in Singapore
Click to view all web page segments
I enjoy hearing from you. If you have comments and suggestions, write me.


Unbuilding Highlights
(Apr 10)
Meeting St. Stories
(Jul 10 2006)
East Bay Stories
(Oct 10 2006)
Drum Island Stories
(Feb 17)
Pearman Bridge Stories
(Apr 3)
Grace Bridge Stories
(Apr 3)
Imposions: Prep and boom
(Mar 27)
Unbuilding Bridge Blog
(July 23 2006)
Unbuilding Challenges
(Mar 13)
Learning Links
(Feb 20)
Unbuilding Stories
(Mar 13)
Video and Sounds
(Feb 28)

November 16, 2005:
More innovation from Bob McCabe's group

One of the challenges with the unbuilding project is that of protecting the environmentally sensitive areas that bound the Cooper River. Roadway removal on the Mt. Pleasant side is a major challenge as there are large wetland areas. As I understand the traditional process, one uses a jack hammer to break up the roadway, with the debris falling into the water below.

I learned that there are actually two classes of structures used in the Pearman Bridge. From the water's edge, concrete girders are supported by concrete piers with a concrete pier cap. However steel girders are used in the bridge section that runs parallel to the cable-stayed part of the Ravenel Bridge. Using a jack hammer to break up the concrete roadway would result in concrete fragments falling into the water below, sinking in the mud bottom and creating a major challenge for removal. Bob's team developed a strategy of hammering a line in the roadway directly over each girder. The result was the only a minimal amount of roadway fell into the river below.

As they completed the steel girder section, a new challenge arose - how to again avoid dropping concrete debris into the shallow riverbed below? Earlier, this week I watched removal of the concrete girders and learned from Bob that his team had developed a new technique for removing roadway segments over the concrete girders. To form the roadway, concrete is poured over a grid of rebar that adds strength to the concrete. The rebar grid is stabilized by coupling it to rows of rebar loops that run the length of the girder. The unbuilding challenge is to remove the roadway while minimizing debris that falls into the river below. Bob's team worked out a strategy that starts with removal of a length of roadway shoulders. Then they cut the roadway into segments (approximately 4' x 10'). First a lateral line is cut perpendicular to the shoulders of the bridge. Then intersecting longitudinal lines are cut. By cutting the longitudinal lines along the center of the concrete girders, the rebar strength is compromised and the roadway segment can be readily extracted. Jack Foley uses a grapple to pick up each section of roadway and move it to his work area. There, with a grapple he breaks the concrete and thus freeing the rebar. The rebar is accumulated and recycled and the concrete is harvested for a reef transplant procedure.

Here is the worksite - the east Ravenel tower to the left, a concrete cutting machine, grapple and shear. Because of safety issues, capturing these images was a challange. Consequently I used a zoom lens which foreshortens the apparent distances. Thus the apparent distances are shorter than the real distances between workers and unprotected boundaries of the work area.

Here, Ted is making the longitudinal cuts along the north side.

Here you can see the matrix formed by the transverse and longitudinal cuts

Then Jack brings his grapple to the to-be-removed segment

reaches under it and gently lifts it up.

and continues to rotate it into a vertical position

so that he can close the grapple jaws and pick the segment up

He then rotates his 345 and moves the roadway segment for later processing.

Here you can see the underside of the segment - which has not seen the sun for 40+ years

Look closely and you can see an exposed section of the rebar grid along the left edge

So with all this cutting, I asked Ted about the lifetime of one of his diamond saw blades and the answer was interesting. Ted gets about 700 feet of cutting done over the concrete girders and about 1500 feet when cutting near the main span. Why? Look at the two concrete samples below. The lower sample uses quartz aggregate and is heavier than the upper sample that uses some sort of black aggregate. (Anyone know what the black rock is?).

While Ted is cutting, Jack is busy eating roadway segments with is shear. By breaking the roadway with his shear - but not cutting it, the rebar is freed. More surgical skills!

After eating all the segments, the rebar fragements are harvested for recycling

Bob inspects the completed section and Ted walks back to get his cutting machine

and the next iteration starts as seen from the Grace Bridge

Once all the roadway is removed between a pair of piers, the concrete girders are harvested see girder harvesting from a few days ago - and then the process starts over again. Nice work!

Click to view all unbuilding web page segments

Creative Commons License
This work is licensed under a Creative Commons License.

Attribution: C. Frank Starmer and Sparky Witte from http://oldcooperriverbridge.org