November 16, 2005:
More innovation from Bob McCabe's group
One of the challenges with the unbuilding project is that of protecting
the environmentally sensitive areas that bound the Cooper River. Roadway
removal on the Mt. Pleasant side is a major challenge as there are large
wetland areas. As I understand the traditional process, one uses a jack hammer
to break up the roadway, with the debris falling into the water below.

I learned that there are actually two classes of structures used in the
Pearman Bridge. From the water's edge, concrete girders are supported
by concrete piers with a concrete pier cap. However steel girders are used
in the bridge section that runs parallel to the cable-stayed part of the
Ravenel Bridge. Using a jack hammer to break up the concrete roadway
would result in concrete fragments falling into the water below, sinking in
the mud bottom and creating a major challenge for removal. Bob's team developed
a strategy of
hammering a line in the roadway directly over each girder. The result
was the only a minimal amount of roadway fell into the river below.
As they completed the steel girder section, a new challenge arose - how
to again avoid dropping concrete debris into the shallow riverbed below?
Earlier, this week I watched removal
of the concrete
girders and learned from Bob that his team had developed a new
technique for removing roadway segments over the concrete girders.
To form the roadway, concrete is poured over a grid of rebar that adds
strength to the concrete. The rebar grid is stabilized by coupling it
to rows of rebar loops that run the length of the girder. The unbuilding
challenge is to remove the roadway while minimizing debris that falls into
the river below. Bob's team worked out a strategy that starts with
removal of a length of roadway shoulders. Then they cut the roadway
into segments (approximately 4' x 10'). First a lateral line is cut
perpendicular to the shoulders of the bridge. Then intersecting
longitudinal lines are cut. By cutting the longitudinal lines along the center
of the concrete girders, the rebar strength is compromised and the roadway
segment can be readily extracted. Jack Foley uses a grapple to pick up
each section of roadway and move it to his work area. There, with a grapple
he breaks the concrete and thus freeing the rebar. The rebar is accumulated
and recycled and the concrete is harvested for a reef transplant procedure.
Here is the worksite - the east Ravenel tower to the left, a concrete
cutting machine, grapple and shear. Because of safety issues, capturing
these images was a challange. Consequently I used a zoom lens which
foreshortens the apparent distances. Thus the apparent distances
are shorter than the real distances between workers and unprotected
boundaries of the work area.

Here, Ted is making the longitudinal cuts along the north side.

Here you can see the matrix formed by the transverse and longitudinal cuts

Then Jack brings his grapple to the to-be-removed segment

reaches under it and gently lifts it up.

and continues to rotate it into a vertical position

so that he can close the grapple jaws and pick the segment up

He then rotates his 345 and moves the roadway segment for later processing.

Here you can see the underside of the segment - which has not seen the sun
for 40+ years

Look closely and you can see an exposed section of the rebar grid along the
left edge

So with all this cutting, I asked Ted about the lifetime of one of his
diamond saw blades and the answer was interesting. Ted gets about 700 feet
of cutting done over the concrete girders and about 1500 feet when cutting
near the main span. Why? Look at the two concrete samples below. The lower
sample uses quartz aggregate and is heavier than the upper sample that uses
some sort of black aggregate. (Anyone know what the black rock is?).

While Ted is cutting, Jack is busy eating roadway segments with is shear.
By breaking the roadway with his shear - but not cutting it, the
rebar is freed. More surgical skills!

After eating all the segments, the rebar fragements are harvested for
recycling

Bob inspects the completed section and Ted walks back to get his
cutting machine

and the next iteration starts as seen from the Grace Bridge

Once all the roadway is removed between a pair of piers, the concrete
girders are harvested
see girder harvesting from a few days ago - and then the process
starts over again. Nice work!